Oman Sohar Project unit 1 and 2 complete 15-day reliability running test successfully

2019-4-22 17:29:06

Oman Sohar Project unit 1 and 2 completed 15-day reliability running test successfully.

At local time 0:45 am of Apr 16, 2019, the project unit 1 completed 15-day reliability running test successfully and unit 1 completed at 8:00 am of Apr 21. During the period, the equipment of electrical primary and the BOP system are running well, the input rate of the monitoring instrument, and the protection and the heat control automatic protection device is 100%. Facing the instructions from LDC for loads changes frequently, project systems are running stably, all technical parameters are excellent. The quality of the steam and water is always within the standard range. The good performance of the units has been highly praised by the owners and third parties.